Central Street Bridge over the Cocheco River

AK Industrial Services (AKIS) removed 4” of existing cast-in-place bridge deck utilizing Ultra High Pressure (UHP) Hydrodemolition. The work was performed over the Cocheco River in Dover, NH. Hydrodemolition was selected to mitigate micro cracking, provide a highly bondable surface for new concrete and to ensure that all unsound concrete was removed.

One of the key challenges was collection of the water and debris at full-depth areas to prevent both from pouring into the river and creating a negative environmental impact. AKIS utilized a 6,000-gallon vacuum tank to collect and dispose of water and debris preventing it from entering the river below

The bridge is also located in the downtown area so there was a great deal of pedestrian traffic directly adjacent to the work zone. AKIS utilized debris screens and temporary fencing to protect the public.

Request A Quote Today!

  • Markets Served

    • Buildings
    • Civil & Infrastructure
    • Industrial
    • Marine
    • Power
  • Member

    • Contact

        AK Industrial Services LLC

      • 617.884.9252
      • info@akservices.com
      • 347 Third Street
      • Everett, MA 02149
    • © 2025 AK Industrial Services LLC. All Rights Reserved. | Website developed by Siphon Marketing